This project will install stockpile canopy covers for the stored materials at the Northside Property Yard to minimize the amount of contaminated stormwater runoff into the adjacent Piney Branch stream.

 Project Details

Project Budget: $250,000

Project Manager: Alan Chen, PE

Anticipated Construction Date: October 2024

Status Summary and Tentative Schedule

August 26, 2024   Town Council Meeting for Approval of Construction Contract
August 15, 2024  Board of Architectural Review Meeting Presentation
August 8, 2024 Open Community Meeting at Mill St NE 
March 2024 Preliminary site survey completed
April 2024 Proposal and cost estimate received