Nutley Street and Marshall Road SW Drainage Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This  project replaces the culvert under Nutley Street SW between Kingsley and Marshall roads SW.

Project Details

Project Budget:  $500,000

Project Manager:  Andrew Jinks, PE

Anticipated Construction Date:  TBD

Nutley Street SW Culvert Plans

Status Summary and Tentative Schedule

June 2012 Town Council approves contract for drainage study
March 21, 2013 On-site citizen meeting
 November 18, 2013 Town Council awards final design contract
 July 10, 2014 60% plans received 
 November 20, 2014 On-site citizen meeting
 May 8, 2015 Design reviewed by VDOT
August 21, 2015   On-site citizen final plan review
 Marcy 7, 2016  Town Council approves funds for additional hydraulic analysis
 March 2017  Pending future CIP funding