Water Main and Appurtenance Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Improvements will consist of a new water meter installation, repairs to aging infrastructure, and provisions to increase functionality of the Town's water system.

Project Details

Project Construction Budget:  $2,500,000

Project Manager:  frank.torre@viennava.gov

Status Summary and Tentative Schedule

July 2023 Dogwood Street SW - between Cottage St. & Center St.  - COMPLETE
 August 2023  Pruitt Court SW - Ware Street to cul-de-sac - COMPLETE
 August 2023  Old Courthouse Road Check Valve and Vault - COMPLETE
 October 2023  Hillcrest Drive SW between Tapawingo Rd.  & Kingsley Rd. - COMPLETE
 Dec. 2023  Polly Street SE between Wolftrap Dr. & Kramer Dr. - COMPLETE
 January 2024  Wolftrap Road Insertion Valves at Westwood Terr and Westwood Forest - COMPLETE
 January 2024  Knoll Street NW between Lewis St. & Nutley St. - COMPLETE
 March 2024   Tapawingo Road SW between Lullaby Ln. & Plum St. - COMPLETE
 March 2024  Albea Court NE and Park Street & Albea Court intersection COMPLETE
 April 2024  Tapawingo Road and Glyndon Street SE VALVES COMPLETE
 June 2024  Westview Court NE COMPLETE
 July 2024  Tapawingo Road SW and Cottage Street SE VALVES COMPLETE
 December 2024  Tapawingo Road SW between Lullaby Lane and Hillcrest Drive COMPLETE
 January 2025  Beulah Road Lakeside Connection (Out of Town) COMPLETE
March 2025 Harmony Drive SW between Cottage Street and Plum Street IN PROGRESS
April 2025 Syracuse Circle (Out of Town) COMPLETE
May 2025 Berea Drive between Carnegie and Wesleyan (Out of Town) ONGOING
 June 2025 Wesleyan Drive (Out of Town) Berea to Cul-de-sac & stream PLANNED
 June 2025 Glyndon Street NE between Ayr Hill to Jean Place PLANNED
 August 2025 Center Street S between Dogwood and Moore PLANNED