Water Main and Appurtenance Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Improvements will consist of a new water meter installation, repairs to aging infrastructure, and provisions to increase functionality of the Town's water system.

Project Details

Project Construction Budget:  $2,500,000

Project Manager:  Christine Horner, PE

Status Summary and Tentative Schedule

Feb. 7, 2022 Council awards improvements and construction contract
October 2022 Tapawingo Road SE from Lullaby Lane to Park Street - COMPLETE
November 2022 Hillcrest Drive SW from Meadow Lane SW to Cul-de-sac - COMPLETE
November 2022 Marian Circle SW - COMPLETE
December 2022 Podium Drive (Out of Town) from Cantata Court to Cul-de-sac - COMPLETE
February 2023 Decree Lane (Out of Town) from Counsellor Drive to Cul-de-sac - COMPLETE
February 2023 Northside Property Yard - Water Valve and Hydrant Improvements - COMPLETE
February 2023 Steeple Run Court (Out of Town) from Garrett Street to Cul-de-sac - COMPLETE
March 2023 Cherry Street SW from Cottage Street SW to Courthouse Road SW - COMPLETE
April 2023 Concerto Court (Out of Town) from Baton Drive to Cul-de-sac - COMPLETE
May 2023 Trumpet Court (Out of Town) and Alto Court (Out of Town) from Percussion Way to respective Cul-de-sacs - COMPLETE
June 2023 Courthouse Road SW - Maple Avenue W to Cherry Street SW - COMPLETE
July 2023 Dogwood Street SW - Cottage Street SW to  Center Street South - COMPLETE
 August 2023  Pruitt Court SW - Ware Street to cul-de-sac - COMPLETE
 August 2023  Old Courthouse Road Check Valve and Vault - COMPLETE
 October 2023  Hillcrest Drive SW from Tapawingo to Kingsley - COMPLETE
 Dec. 2023  Polly Street SE from Wolftrap to Kramer - COMPLETE
 January 2024  Wolftrap Road Insertion Valves at Westwood Terr and Westwood Forest - COMPLETE
 January 2024  Knoll Street NW from Lewis to Nutley - PLANNED
 March 2024   Tapawingo Road SW from Lullaby to Plum - PLANNED