The 300 block of Glyndon Street, NE, is an existing "shoulder and ditch" roadway with minimal drainage infrastructure.  In heavy rains, stormwater flows across the street and floods private property on the west side.  Work on the project was paused until additional funding was available.  In 2024, the American Rescue Plan Act (ARPA) provided the necessary funds to complete the design and fund the construction.  This project includes curb and gutter on both sides of the roadway and sidewalk on the south side of the roadway from Ayr Hill Avenue to Jean Place.  Note:  work in front of the Glyndon Park parking lot is not included with this project.  Modifications to the parking lot, if any, will be made by Parks and Recreation.  New storm drain pipes and inlets will be constructed within the project limits.  

A separate project, Church Street, NE, Sidewalk Improvement Project, includes construction of curb, gutter and sidewalk on Glyndon Street from Ayr Hill Avenue to Maple Avenue.

Project Details

Project budget:  $1,800,000Vicinity Map

Contact:  DPW@viennava.gov

Anticipated construction date:  Spring 2025

Glyndon Street NE link to Plans

 

 

 

 

 

 

 

Status Summary and Tentative Schedule

Nov. 16, 2015 Engineering services contract awarded
June 22, 2016 Drainage study received
 July 20, 2016 Citizens exhibit received
 Feb. 21, 2018 30% engineering plans received
 Oct. 10, 2018 60% engineering plans received
 2023 - 2024 Allocation of ARPA Funding to project
Apil 23, 2024 Final engineering plans complete
Nov. 18, 2024 Town Council approves construction contract
Sprint 2025 Construction begins